Customer: Vehicle Access Systems Technology
Location: Taicang, China
Project Description: Plant Capacity Increase and Upgrade
Including the Following Renovations:
- Modification of Existing Conveyor System for Stability
- Rework of Existing Sludge System
- Installation of (2) New Clearcoat Automated Spray Booths
- Building Expansion to Accomodate New Prime Booths
- Installation of (2) New Prime Automated Spray Booths
- Paint Circulation System Upgrades and Expansion
- Topcoat & Prime Oven Modifications to Improve Efficiency
- Installation of New RASH & FASH Units
- Conveyor Additions / Rearrangements
PSE Role:
- Existing Paint Facility Health Assessment
- Concept Planning, Development and Finalization
- Detailed Engineering and Bid Package Development
- Sub-contractor Coordination
- Field / Site Management
- Facility Validation and Launch Coordination